ContingencyThe schedule that had first gas in mid November included an 8 week contingency for delays etc. Assuming they used up 4 of those weeks for the late arrival of the CPF in Alexandria and no further delays, would suggest that they could get it done by mid October which would be next week. Note that the compressor installation is not as critical as they will have enough natural pressure from the wells for the first few months so they don't need it at startup. So why is the stock sliding backwards? |